Fits the upper fixed bar and boiler mounting bracket.

Check in this order

  1. Place the upper fixed bar between the tops of the 2 post bars. Point its arrow mark up.
  2. Affix 4 fixed brackets with 4 M10 bolts (3 in) to the post bars and 2 M10 bolts (4 in) to the upper bar.
  3. Fix the mounting bracket and rubber pad supplied with the boiler to the middle of the upper bar with 4 M8 bolts (2.8 in).

Applies to: Ready-Link Commercial rack, upper bar

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Ready-Link Commercial Rack System installation guide, p. 2. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.