Assembling the pipe support brackets

Ready-Link Commercial

What is going on

Mounts heating supply, heating return and gas pipe supports.

Check in this order

  1. Fix the heating supply bracket to a post bar with 3 M10 bolts (3 in).
  2. Fix the heating supply bracket to the front lower bracket with 1 M10 bolt (1 in).
  3. Fix the heating return bracket to a post bar with 3 M10 bolts (3 in).
  4. Fix the heating return bracket to the front lower bracket with 2 M10 bolts (1 in).
  5. Fix the gas pipe bracket to a base frame with 2 M10 bolts (3 in).
  6. Repeat the first three steps for the other foot bar.

Applies to: Ready-Link Commercial rack, pipe supports

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Ready-Link Commercial Rack System installation guide, p. 2. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.