Glow Brand · Boiler · Startup

Power-up and de-air

B85/B120/B160

What happens, in order

  1. Power on starts the de-air sequence automatically
  2. Circulators cycle off and on for about 14 minutes to free air from the heat exchanger
  3. Display shows dAir during de-air; the boiler ignores heat calls until it finishes
  4. Hold CH down and DHW down together for 3 seconds to cancel de-air if the system is already purged
  5. Installer can turn de-air off with parameter 2.139
  6. After de-air the boiler returns to standby and waits for a CH or DHW demand

Timings and thresholds

ItemValue
De-air duration14 min
Cancel de-airhold CH V + DHW V for 3 s

Applies to: B85, B120, B160

Models

B85B120B160

More Glow Brand boiler sequences

Take it to the job

Sequences of operation, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Glow Brand B85/B120/B160 Installation and Operating Manual (sections 10.2, 11.7, 11.8, 11.10, 12.1). Written in our own words; timings can differ by model and software version, so check the manual for your exact unit.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.