Weil-McLain · Boiler troubleshooting

Water chiller piping, primary/secondary

SVF 500/600 Series 1

What is going on

For systems using a chilled water loop. The chiller must be piped in parallel with the boiler, and valves must keep chilled medium out of the boiler.

Check in this order

  1. Pipe the chiller in parallel with the boiler, as in Figure 19.
  2. Install valves that prevent chilled medium from entering the boiler.
  3. Install a separate circulator for the chilled water loop if the heating zones use circulators.
  4. Install a check valve and a balancing valve in the chilled loop as shown.
  5. Install a flow/check valve on the boiler outlet to prevent gravity circulation during DHW heating.
  6. If the boiler feeds coils in air handlers that can see refrigerated air, use flow control valves or other automatic means to stop gravity circulation during cooling.
  7. If antifreeze is used, check its effect on circulator sizing and DHW performance. Use only antifreeze listed on p. 131.

Applies to: SVF 500/600 boilers in systems with a water chiller

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: SVF 500/600 Series 1 Boiler Manual, p. 27. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.