Weil-McLain · Boiler troubleshooting

Vent and air termination location clearances

SlimFit Series 2

What is going on

Applies to direct vent and direct exhaust terminations. Vent and air terminations must sit at least 12 in above grade and above the snow line. Keep them clear of snow buildup. Keep the termination at least 4 ft horizontally from electrical meters, gas meters, regulators and relief equipment, and never directly above or below them unless the 4 ft horizontal distance is kept. Also meet the clearances to walkways, buildings, openable windows and building openings set by NFGC/ANSI Z223.1 or CSA B149.1. Check the full clearance figure (Figure 26 for direct exhaust, Figure 33 for direct vent) before finalising placement.

Check in this order

  1. Confirm the termination is at least 12 in above grade and the snow line.
  2. Confirm at least 4 ft horizontal clearance from gas meters, electrical meters, regulators and relief equipment.
  3. Confirm clearance from openable windows, building openings and walkways per the figure and local code.
  4. Place the termination where foreign objects and leaves or sediment will not build up on it.
  5. For Canadian installs, use a ULC S636 compliant vent kit and follow CSA B149.1.

Applies to: SlimFit 1000-2000 Series 2 direct exhaust and direct vent terminations

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: SlimFit-1000-2000 Boiler Manual 550-100-561/1225, p. 32-33, 38-39. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.