What is going on

General rules for routing vent and air piping from the boiler to the termination.

Check in this order

  1. Use a locking collar on every polypropylene vent joint. Missing collars can cause leaks.
  2. Use sweep elbows only. Do not use short-radius elbows.
  3. Add a vent adapter or reducer if needed, following the vent manufacturer's instructions.
  4. Slope horizontal vent piping back toward the boiler at least 1/4 in per foot, or steeper if the vent maker requires it.
  5. Keep total vent length within the maximum in Figure 22 (p. 36). Reduce the maximum for each elbow as the figure shows.
  6. Install the termination before running piping from the boiler to it.

Applies to: SVF 500/600 Category IV direct vent and direct exhaust piping

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Weil-McLain SVF 500/600 Series 1 boiler manual, p. 57-58. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.