What is going on
The Ultra must sit on its own boiler loop, piped primary/secondary. Wrong tee connections or undersized loop pipe cause flow problems.
Likely causes
- Boiler loop connected to the run of the tees instead of the branch
- Primary/secondary tees more than 12 in. apart
- Boiler loop pipe smaller than the minimum
- Boiler circulator used for the system instead of the boiler loop
Check in this order
- The boiler loop must enter the tees through the branch connection, never the straight-through run.
- Keep the two system tees no more than 12 in. apart.
- Boiler loop minimum pipe size Ultra-80/105 1 in.; Ultra-155/230 1-1/4 in.; Ultra-299/399 1-1/2 in.
- The circulator shipped with the boiler is only for the boiler loop. System, zone and DHW circulators are supplied by the installer.
- Optional Easy-Up manifolds 383-500-649 (1-1/4 in., Ultra-80/105) and 383-500-661 (1-1/2 in., Ultra-155 to 399).
Applies to: Weil-McLain Ultra Series 3 gas boilers (Ultra-80 to Ultra-399)
More boiler guides
Related
Weil-McLain error codes · Weil-McLain parts · Weil-McLain tips · Calculators and reference tables
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: Weil-McLain Ultra Series 3 Quick-Start installation guide and material checklists C-1120 (0910), water piping panel. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.