Startup check-out verification

SlimFit Series 3

What is going on

Final checklist to complete before handing the boiler over after startup.

Check in this order

  1. Confirm the control is set for the correct boiler model.
  2. Confirm boiler and heat distribution units are filled with water, water chemistry is checked (page 83), automatic air vents are open one full turn, and air is purged from the system and gas piping.
  3. Check for gas leaks and confirm the condensate trap is primed.
  4. Confirm the propane conversion kit and label are installed if the boiler runs on propane. The boiler ships for natural gas only.
  5. Check thermostat circuit wiring for stray voltages.
  6. Check burner flame and combustion (page 86) and measure natural gas input (page 86).
  7. Check incoming gas pressure against page 49 for natural gas or propane.
  8. Verify control operation for space heating and DHW if used.
  9. Test any additional field-installed limits. The boiler should shut off when they trip, and they should lock out in the intended reset mode.
  10. Set field limits to system temperature requirements and balance valves and zone flows as needed.
  11. Set thermostat heat anticipator if the thermostat has one (page 63).
  12. Cycle the boiler with the thermostat and DHW aquastat if installed. Raise to the highest setting and confirm normal startup, then lower to the lowest setting and confirm shutdown.
  13. Observe several operating cycles for proper operation.
  14. Set room thermostat and DHW aquastat to the desired temperatures.
  15. Review all shipped instructions with the owner.
  16. Fill in the installation certificate (page 123) and the warranty registration, and return the instructions to the envelope or boiler housing.

Applies to: SlimFit 550 and 750 Series 3

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: SlimFit series3 commercial gas-fired water boiler boiler manual, p. 89. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.