Sidewall vent termination location and clearances
What is going on
Choose a termination spot that stays clear of debris, snow and other terminations.
Check in this order
- Pick a location where foreign objects and leaf or sediment buildup are unlikely.
- Keep the termination above grade and snow line, and keep vent and air openings clear of snow.
- Place the boiler so the vent can be routed from the boiler vent connection to the chosen sidewall spot without exceeding the Figure 22 maximum length (p. 36).
- Terminate all vent and air inlet pipes at the same height.
- Keep at least 12 in between the edge of a vent opening and an adjacent termination (Figure 48, p. 58).
- For other appliances, keep at least the clearance shown. Their installation must also follow this manual.
- In the US, meet the clearances in Figure 48 and Figure 36 (p. 49).
- In Canada, meet CAN/CSA B149.1 or B149.2 and use a ULC S636-compliant vent kit.
- The air inlet is part of a direct vent connection and is not treated as a forced air intake for spacing from adjacent boiler vents.
Applies to: SVF 500/600 Category IV direct vent, sidewall termination, single or multiple boilers
More boiler guides
Related
Weil-McLain error codes · Weil-McLain parts · Weil-McLain tips · Calculators and reference tables
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: Weil-McLain SVF 500/600 Series 1 boiler manual, p. 58. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.