Weil-McLain · Boiler troubleshooting

Sidewall vent termination location and clearances

SVF 500/600 Series 1

What is going on

Choose a termination spot that stays clear of debris, snow and other terminations.

Check in this order

  1. Pick a location where foreign objects and leaf or sediment buildup are unlikely.
  2. Keep the termination above grade and snow line, and keep vent and air openings clear of snow.
  3. Place the boiler so the vent can be routed from the boiler vent connection to the chosen sidewall spot without exceeding the Figure 22 maximum length (p. 36).
  4. Terminate all vent and air inlet pipes at the same height.
  5. Keep at least 12 in between the edge of a vent opening and an adjacent termination (Figure 48, p. 58).
  6. For other appliances, keep at least the clearance shown. Their installation must also follow this manual.
  7. In the US, meet the clearances in Figure 48 and Figure 36 (p. 49).
  8. In Canada, meet CAN/CSA B149.1 or B149.2 and use a ULC S636-compliant vent kit.
  9. The air inlet is part of a direct vent connection and is not treated as a forced air intake for spacing from adjacent boiler vents.

Applies to: SVF 500/600 Category IV direct vent, sidewall termination, single or multiple boilers

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Weil-McLain SVF 500/600 Series 1 boiler manual, p. 58. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.