Sidewall separate pipes: termination installation
What is going on
Mounting the vent and air pipes through a sidewall with stop plates and termination elbows.
Check in this order
- Cut a hole for the air pipe per the air pipe maker's size.
- Cut the vent hole at least 3/8 in larger than the pipe in combustible construction, or per the vent maker in noncombustible construction, and set a corrosion-resistant thimble.
- Install corrosion-resistant stop plates from the vent maker, with holes just larger than the vent pipe.
- Insert vent and air pipe from outside until female-end shoulders rest against the outer stop plates.
- Attach the exterior pipe and the vent termination elbow (outward facing) and air termination elbow (down-turned).
- Fit a bird screen supplied by the installer in the open end of the termination.
- Brace individual pipes at up to 24 in spacing and maintain all clearances and lengths.
- Seal the exterior openings with exterior caulk.
Applies to: SVF direct vent sidewall separate pipes
More boiler guides
Related
Weil-McLain error codes · Weil-McLain parts · Weil-McLain tips · Calculators and reference tables
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: SVF 500/600 Series 1 Boiler Manual, p. 51. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.