Weil-McLain · Boiler troubleshooting
Sidewall concentric vent termination - wall opening and assembly
What is going on
Prepare the wall penetration and mount the concentric termination so it cannot shift and blocked air passages are avoided.
Check in this order
- Assemble the termination as described in the concentric termination section (p. 54).
- Use a thimble with a 4-1/2 in hole for the wall penetration. This is the preferred method.
- If no thimble is used, cut a hole no larger than 4-3/4 in with a hole saw. The finished hole must give a solid stop for the rain cap ribs.
- Confirm the wall is strong enough that the rain cap cannot be pushed inward from outside.
- Position the termination so the rain cap sits against the outside wall or outer thimble plate.
- Cover the exposed end of the assembly while it is pushed through the wall so debris stays out of the pipes.
- Do not alter the concentric assembly. Once the rain cap is cemented, blockages cannot be cleared, so replace the assembly if it must be cleaned or removed.
- Use only the vent materials and kits listed in Table 9 (p. 33).
Applies to: SVF 500/600, Category IV direct vent, sidewall concentric termination
More boiler guides
Related
Weil-McLain error codes · Weil-McLain parts · Weil-McLain tips · Calculators and reference tables
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: Weil-McLain SVF 500/600 Series 1 boiler manual, p. 56. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.