What is going on

Finish the concentric termination: support, screen, rain cap and weatherproofing.

Check in this order

  1. Support the termination with brackets and bracing per the kit instructions so it cannot slip or move.
  2. Do not let the vent or air piping rest its weight on boiler fittings. Support it independently.
  3. Use clamps on the outside pipe that do not cut into the pipe or leave sharp edges.
  4. Keep the finished termination piping to the dimensions in Figure 36 (p. 49).
  5. Place the bird screen on the end of the inner pipe, or per the kit instructions for polypropylene kits, then cement the rain cap in place (Figure 43, p. 54).
  6. Seal all exterior openings thoroughly with exterior caulk.
  7. Install pipe supports every 5 ft on horizontal and vertical runs, and a hanger within 6 in of any upturn.

Applies to: SVF 500/600, Category IV direct vent, sidewall concentric termination

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Weil-McLain SVF 500/600 Series 1 boiler manual, p. 57. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.