  1. Locate the concentric termination per the clearance table and the multiple-boiler spacing rules.
  2. Assemble the termination as described for concentric terminations.
  3. Use a thimble with a 4-1/2 in hole as the preferred wall penetration.
  4. If not using a thimble, cut the wall hole with a hole saw no larger than 4-3/4 in diameter, leaving a solid stop for the rain cap ribs.
  5. Make sure the wall is strong enough that the rain cap cannot be pushed inward from outside.
  6. Secure the termination so the rain cap ribs rest against the outside wall or outer thimble plate.
  7. Protect the exposed assembly with plastic during insertion through the wall penetration.
  8. Install the vent and air piping from the boiler to the concentric termination after the termination is mounted and secured.
  9. Support the vent and air pipes every 5 ft, and brace the wall with a wall brace per the installer or vent maker instructions.

Applies to: SVF direct vent sidewall concentric (Category IV)

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: SVF 500/600 Series 1 Boiler Manual, pp. 55-56. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.