Four-step order for control setup from the manual.

Check in this order

  1. Step 1 Determine input and output needs (thermostats, remote contacts, end switches and what each output must run, such as a pump or air louver).
  2. Step 2 Install the boiler per the boiler manual, then wire control inputs and outputs for the Step 1 purposes.
  3. Step 3 Follow the boiler manual to start up and power the boiler.
  4. Step 4 Use the Wizard (recommended) or enter control parameters manually.

Applies to: SVF control commissioning

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: SVF 500/600 Series 1 boiler manual, p. 85. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.