Weil-McLain · Boiler troubleshooting
Setting up the boiler (commissioning order)
What is going on
Four-step order for control setup from the manual.
Check in this order
- Step 1 Determine input and output needs (thermostats, remote contacts, end switches and what each output must run, such as a pump or air louver).
- Step 2 Install the boiler per the boiler manual, then wire control inputs and outputs for the Step 1 purposes.
- Step 3 Follow the boiler manual to start up and power the boiler.
- Step 4 Use the Wizard (recommended) or enter control parameters manually.
Applies to: SVF control commissioning
More boiler guides
Related
Weil-McLain error codes · Weil-McLain parts · Weil-McLain tips · Calculators and reference tables
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: SVF 500/600 Series 1 boiler manual, p. 85. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.