Roof penetration and vent support for vertical direct exhaust
What is going on
Size the roof hole at least 0.5 in larger than the vent pipe. For 6 in PVC or PP, use a 7 in hole. Insert a galvanized thimble and use flashing and boots sized for the vent and air pipes. Hanger supports go within 6 in of any upturn, pipe supports every 5 ft on horizontal and vertical runs, and horizontal pipe slopes down toward the boiler at least 1/4 in per foot.
Check in this order
- Cut a roof hole at least 0.5 in larger than the vent pipe (7 in for 6 in PVC or PP).
- Insert a galvanized metal thimble.
- Install flashing and sealing boots sized for the vent and air pipe.
- Place a hanger support within 6 in of any upturn.
- Support runs every 5 ft on horizontal and vertical sections.
- Slope horizontal pipe toward the boiler at least 1/4 in per foot.
Applies to: Vertical direct exhaust installations
More boiler guides
Related
Weil-McLain error codes · Weil-McLain parts · Weil-McLain tips · Calculators and reference tables
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: SlimFit series 3 commercial gas-fired water boiler manual, p. 27. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.