What is going on

Leave the boiler in its carton and on the pallet until the site is ready. Move the carton and pallet next to the location, then remove the carton. Remove the boiler from the pallet by tilting it side to side over boards and sliding it off. Do not drop it or bump the jacket.

Likely causes

  • Dropping or bumping the boiler can damage it

Check in this order

  1. Leave the boiler in its carton on the pallet until the site is ready.
  2. Move the carton and pallet to the location and remove the carton.
  3. Tilt the left side up and put a board under the left legs, then tilt the right side up and put a board under the right legs.
  4. Slide the boiler backwards off the pallet into position.
  5. Check that the boiler is level. Shim the legs if needed. Do not alter the legs.

Applies to: CGi-25 to CGi-8

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: CGi Series 5 Gas-Fired Water Boiler Manual, p. 16. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.