Move the boiler off the pallet safely and set it level. Do not alter the leg height.

Check in this order

  1. Keep the boiler in its carton on the pallet until the site is ready.
  2. Move the carton and pallet next to the install spot, then remove the carton.
  3. Tilt one side up and put a board under those legs, then tilt the other side and do the same.
  4. Slide the boiler off the pallet into position. Do not drop it or bump the jacket.
  5. Check level. Shim the legs if needed. Do not change the legs.

Applies to: CGi-25 to CGi-8

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: CGi Series 5 Gas-Fired Water Boiler boiler manual, p. 16. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.