Weil-McLain · Boiler troubleshooting
Multiple boiler direct exhaust sidewall terminations
What is going on
Terminate each boiler's vent on the wall with the same clearances as a single boiler, following the typical layout.
Check in this order
- Place each wall penetration to meet the minimum U.S. clearances in Figure 28, p. 44.
- For Canadian installs, meet the clearances in CAN/CSA B149.1 and use a ULC S636-compliant vent kit.
- Keep all vent terminations at the same height and at least 12 in above grade or snow line.
- Follow the multiple-boiler layout in Figure 29, p. 45.
Applies to: Multiple SVF boilers, direct exhaust sidewall
More boiler guides
Related
Weil-McLain error codes · Weil-McLain parts · Weil-McLain tips · Calculators and reference tables
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: SVF 500/600 Series 1 Boiler Manual, p. 44. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.