Wiring requirements from the ladder diagrams for CGi-25 to CGi-8 spark-ignited pilot models.
Check in this order
- Wire to the NEC and any applicable national, state or local codes.
- Do not field-replace pilot lead wires. Replace the pilot assembly if they are damaged.
- If any original factory wire must be replaced, use at least 105°C wire or equivalent. Wires to the rollout TFE must be 200°C or equivalent.
- For multiple zones, use zone valves or circulators and follow the component maker's instructions and this manual.
- Wire any extra limit controls (low water cut-off, high temperature limit, etc.) to terminal P4 on the control.
- Set the model configuration with the configuration plug (P13); C13-2 through C13-5 are used for this. The diagram shows the natural gas/propane configuration.
Applies to: CGi-25, -3, -5, -6 (Figure 32); CGi-4, -7, -8 (Figure 33)
More boiler guides
Related
Weil-McLain error codes · Weil-McLain parts · Weil-McLain tips · Calculators and reference tables
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: CGi Series 5 Gas-Fired Water Boiler Boiler Manual, p. 48-49. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.