A gas vent through an exterior wall must not end next to the wall or under eaves, parapets, balconies or decks. Figure 11 gives the minimum termination clearances, but the figure values are not readable in the extracted text.

Check in this order

  1. Check the termination location against Figure 11 before fixing the vent.
  2. Do not terminate the vent beside the wall or under any building extension.
  3. Confirm the clearances on the drawing before final installation.

Applies to: CGi-25 to CGi-8

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: CGi Series 5 boiler manual, p. 24. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.