What is going on
The propane orifice sits in the counterbore of the venturi gas flange. The gas train adapter flange is removed to reach it.
Check in this order
- Remove the front door by turning the two rotary latches, then lift the door off.
- Loosen the four gas train adapter screws and nuts (4 mm Allen and 8 mm wrench) and remove the gasket.
- Check the gasket between the adapter flange and venturi flange. It must be in good condition and installed, or the joint can leak gas.
- Pull the gas train forward and support it.
- Insert the propane orifice into the venturi flange counterbore.
- Reposition the gasket and adapter against the venturi flange.
- Secure with the four screws and nuts. Do not over-tighten, but make sure the joint is secure (1.5 N-m / 13 in-lbs / 1 ft-lb).
- Reinstall the front door when finished.
Applies to: SF-550 and SF-750 propane
More boiler guides
Related
Weil-McLain error codes · Weil-McLain parts · Weil-McLain tips · Calculators and reference tables
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: SlimFit 550/750 Series 3 boiler manual, p. 9. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.