What is going on

Pressure test the boiler before permanent water or gas piping and electrical supply are connected. Do not exceed 120 psig.

Check in this order

  1. Pipe the 2 inch tee, bushing and 3/4 inch nipple to the supply connection. Plug the end of the supply tee.
  2. Attach a 3/4 inch shutoff valve to the nipple, then a 2 inch tee to the return.
  3. Add a bushing and 3/4 inch drain valve to the return tee, and plug its end.
  4. Connect a hose from the drain valve to fresh water. Use pipe dope sparingly.
  5. Open the supply and return shutoff valves, then slowly fill the boiler through the drain valve.
  6. When water reaches the top shutoff valve, let it run until all air is out of the heat exchanger. Close the drain valve, then the top shutoff valve.
  7. Raise pressure until the P/T gauge reads 120 psig, but no higher.
  8. Hold for 10 minutes and keep the boiler attended. Confirm pressure holds and check for leaks.
  9. Drain through the drain valve, remove the test fittings, and remove the 3/4 inch shutoff valve from the relief nipple.
  10. Do not use petroleum-based cleaners or sealants in the system. Repair any leak immediately.

Applies to: All SlimFit boilers

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: SlimFit 550/750 Series 3 boiler manual, p. 11. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.