What is going on

Connect the gas line at the boiler without twisting the factory gas connection.

Check in this order

  1. Use two wrenches one holds the boiler gas connection still while the other tightens the joint.
  2. Install a union for servicing where required.
  3. Install a manual gas shut-off valve in the supply line within 6 ft of the boiler. In Canada, the installer must identify this valve.
  4. Support the gas piping with hangers. Do not support it from the boiler or its accessories.
  5. Use pipe dope compatible with propane, since natural gas may contain some propane. Apply sparingly to male threads only so it does not block gas flow.
  6. The boiler ships ready for natural gas only. Install the propane conversion kit before connecting propane (see p. 16).
  7. If any factory gas connection is altered, check for leaks before operating the boiler (p. 63).

Applies to: SVF 500/600 gas supply piping

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Weil-McLain SVF 500/600 Series 1 boiler manual, p. 62. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.