Gas supply pipe sizing and multiple boiler manifolds
What is going on
Size the gas supply from the meter to the boiler and set up manifolds for multiple boilers.
Check in this order
- Find the total input in Btuh for all connected appliances and divide by 1,000 to get approximate cubic feet per hour of natural gas.
- Size pipe from the meter outlet to the boiler using Table 11 (p. 64). Table 11 applies only to natural gas with specific gravity 0.60 and a 0.30 in W.C. pressure drop.
- Add the straight pipe length to the equivalent lengths of fittings from Table 12 (p. 64) to get total gas pipe length.
- Use a 100% lock-up regulator in the gas supply line with properly sized pipe.
- For propane, convert the boiler first (p. 16), then have the gas supplier size pipes, tanks and regulators.
- For manifolded multi-boiler gas supply, size the main as above, then provide a manual shutoff valve, union and sediment trap (at least 3 in below the tee) at each boiler.
- Make sure the piping delivers the minimum pressure at each boiler (p. 63).
- For other sizing details, refer to ANSI Z223.1/NFPA 54 or, in Canada, CAN/CSA B149.1.
Applies to: SVF 500/600 gas supply sizing, natural gas and propane
More boiler guides
Related
Weil-McLain error codes · Weil-McLain parts · Weil-McLain tips · Calculators and reference tables
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: Weil-McLain SVF 500/600 Series 1 boiler manual, p. 64. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.