Layout requirements when several boilers share one gas supply line.
Check in this order
- Size the manifold supply piping as for a single boiler.
- Install a manual shutoff valve, union and sediment trap (at least 3 in. below the tee) at each boiler.
- Confirm the piping delivers the minimum gas pressure required at each boiler (see p. 63).
Applies to: Multi-boiler gas supply
More boiler guides
Related
Weil-McLain error codes · Weil-McLain parts · Weil-McLain tips · Calculators and reference tables
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: SVF 500/600 Series 1 Boiler Manual, p. 64. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.