What is going on

Complete these checks after the system is filled and before the boiler is started. Look for leaks, make sure the vent and air piping are sound, and confirm the gas and electrical connections are correct.

Check in this order

  1. Set up the control and confirm every setting is correct.
  2. Confirm the boiler and system are full of water and components are set for operation.
  3. Purge air from the system using the manual vents.
  4. Check all system piping for leaks and fix any leak before running the boiler.
  5. Fill the condensate trap with water.
  6. Confirm electrical connections are correct and tight.
  7. Inspect vent and air piping for corrosion, damage or sagging, and confirm it is installed per the manual.
  8. Check pressure switch sense hoses are on the correct fittings and in good condition.
  9. Before startup, smell near the floor and around the boiler for gas odour, and do not start if a leak is suspected.

Applies to: SlimFit Series 2 commissioning

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: SlimFit Series 2 boiler manual 550-100-561/1225, p. 81. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.