Field wiring: power, circulator and strain relief

SlimFit Series 2

What is going on

Turn off power at the service panel before wiring. Use N.E.C. Class 1 wiring and type 105 C wire if replacing original wiring. Bond and ground the boiler per code. Use strain relief at the cabinet knockouts. The 24 V transformer output must not power external devices that are not listed in the manual. The boiler circulator relay on the expansion module is dry contact rated 10 A and needs external 120 VAC supply for the pump.

Check in this order

  1. Turn off electrical power at the service entrance panel.
  2. Feed line and low-voltage wiring through the top cabinet knockouts and install strain relief.
  3. Connect 120 VAC power to the boiler.
  4. Provide external 120 VAC power for the boiler circulator and wire it through the EP7 terminal, interrupting the pump's hot line.
  5. Confirm the circulator load is within the 10 A relay rating.
  6. Do not connect external devices to the 24 V transformer output unless listed in the manual.
  7. Ground and bond the boiler per code.

Applies to: SlimFit SF1000, SF1500, SF2000 field wiring

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Weil-McLain SlimFit Series 2 boiler manual, p. 47. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.