Weil-McLain · Boiler troubleshooting
Field wiring for 120 VAC power and service switch
What is going on
The boiler is powered by 120 VAC through the junction box. A fused disconnect or service switch of 15 amp is recommended. Where local code bars a switch on the boiler, use a remote service switch.
Check in this order
- Connect 120 VAC power wiring as shown in Figure 27 on page 41.
- Mount a 15 amp fused disconnect or service switch on the junction box if allowed.
- If local code prohibits a switch on the boiler, install a 2 x 4 cover plate on the junction box.
- Mount the service switch remotely as the code requires.
Applies to: CGi Series 5 boilers
More boiler guides
Related
Weil-McLain error codes · Weil-McLain parts · Weil-McLain tips · Calculators and reference tables
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: CGi Series 5 gas-fired water boiler manual, p. 42. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.