Field wiring for 120 VAC power and service switch

CGi Series 5

What is going on

The boiler is powered by 120 VAC through the junction box. A fused disconnect or service switch of 15 amp is recommended. Where local code bars a switch on the boiler, use a remote service switch.

Check in this order

  1. Connect 120 VAC power wiring as shown in Figure 27 on page 41.
  2. Mount a 15 amp fused disconnect or service switch on the junction box if allowed.
  3. If local code prohibits a switch on the boiler, install a 2 x 4 cover plate on the junction box.
  4. Mount the service switch remotely as the code requires.

Applies to: CGi Series 5 boilers

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: CGi Series 5 gas-fired water boiler manual, p. 42. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.