Wiring must meet N.E.C. Class 1. The boiler must be electrically grounded per NEC / ANSI/NFPA 70. Comply with NEC and any national, state or local codes. The boiler ships with controls wired except the spill switch and vent damper. Shut off power at the service entrance before making any connections.

Check in this order

  1. Turn off power at the service entrance panel before any electrical work.
  2. Confirm the boiler is electrically grounded as NEC requires.
  3. Use N.E.C. Class 1 wiring for field connections.
  4. Wire the spill switch and vent damper, which are not factory-wired.
  5. Use the boiler wiring diagrams on pages 46 and 48 for the spark-ignited pilot model.

Applies to: CGi Series 5 boilers, spark-ignited pilot

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: CGi Series 5 gas-fired water boiler manual, p. 41. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.