Weil-McLain · Boiler troubleshooting

Direct vent vertical terminations (vent and air)

SVF 500/600 Series 1

What is going on

Vertical direct vent installs use separate vent and air terminations, which can be roof or sidewall for the air side.

Check in this order

  1. Terminate all vent pipes at the same height and all air pipes at the same height.
  2. Cut separate penetrations for the air pipe and the vent pipe, and thimble the vent hole.
  3. For a vertical air termination, fit flashing and sealing boots and install a bird screen in the open end.
  4. Keep 12 in minimum vertically from the vent outlet to any air inlet.
  5. Keep 12 in minimum between the edge of one boiler's air intake and the adjacent vent of another boiler.
  6. For multiple boilers, space flue vents at least 6 in apart from other flue vents, and air terminations at least 6 in apart from other air terminations. Keep 12 in horizontal between flue vents and air terminations.

Applies to: Direct vent vertical termination, Category IV

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: SVF 500/600 Series 1 Boiler Manual, p. 46. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.