Direct exhaust vertical vent termination: location and clearances

SlimFit Series 3

What is going on

Clearances for a vertical (roof) direct exhaust termination. The vent must end in a coupling, and all clearances must be met for the roof, walls, openings and air inlets.

Likely causes

  • Termination too low on the roof or too close to a snow line
  • Termination in a recessed area or near a forced air intake

Check in this order

  1. Terminate at least 12 in above the roof or snow line, as shown in the figure.
  2. Keep it at least 6 ft from adjacent walls.
  3. Keep it at least 5 ft below any roof overhang.
  4. Keep it at least 3 ft above any forced air intake within 10 ft.
  5. Keep it at least 48 in below or horizontally from any door, window or other gravity air inlet.
  6. Keep it at least 4 ft horizontally from electric meters, gas meters, regulators, relief valves or other equipment.
  7. End the vent piping in a coupling with a bird screen fitted.
  8. Keep the termination away from wind eddies, building corners, adjacent surfaces and recessed areas.
  9. Locate or guard the vent so condensate does not damage exterior finishes.
  10. Do not extend exposed vent pipe beyond the length shown in the figure.

Applies to: SF-550 and SF-750 direct exhaust, vertical termination

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: SlimFit series 3 commercial gas-fired water boiler manual, p. 34-35. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.