General install rules for direct exhaust venting: no mixed vent materials, sealed joints, correct slope, clearances to combustibles, and approved penetrations.

Check in this order

  1. Do not mix vent types or manufacturers.
  2. Clean all joints and seal them with the vent maker's sealant. Do not use screws.
  3. Install the vent with seams on top of horizontal runs.
  4. Keep at least 2 inches from combustible material to the vent pipe.
  5. For vertical venting, pass the pipe through the roof flashing, jacket or thimble as the vent maker directs.
  6. For sidewall venting, end the vent at least one foot above the expected snow line.
  7. Install the horizontal drain tee as close to the boiler as possible, in the first horizontal run.
  8. Do not exceed the maximum vent length in Table 6 on page 20.
  9. Do not seal the slip connector to the inside or outside wall plate.
  10. Where the vent passes through a noncombustible wall, make the hole large enough for the pipe or slip connector.

Applies to: CGi-25 to CGi-8

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: CGi Series 5 boiler manual, p. 25. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.