Connect the direct exhaust vent starter

CGi Series 5

What is going on

Attach the vent starter to the blower housing outlet and seal it. Sealant method varies by vent brand.

Check in this order

  1. Select the vent manufacturer and get all components for the location and venting method.
  2. Connect the vent starter from that same manufacturer to the blower housing outlet.
  3. Keep 2 inch clearance from combustibles to the vent pipe.
  4. Seal with the high temperature sealant the vent maker specifies, using a 3/8 inch bead. FasNSeal does not need sealant.
  5. Tighten the band clamp strap until snug around the blower housing.
  6. Put the blower cover back on and fasten it with four screws.

Applies to: CGi-25 to CGi-8

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: CGi Series 5 Gas-Fired Water Boiler boiler manual, p. 22. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.