What is going on

Gas piping must be leak-checked before the boiler is placed in operation. Remove the jacket front panel and follow the gas supply piping layout in Figure 25.

Check in this order

  1. Remove the jacket front panel.
  2. Install a drip leg at the inlet of the boiler gas connection. Extend it to the floor with pipe between cap and tee if the local utility requires it.
  3. Install a ground joint union for servicing where required.
  4. Install a manual shutoff valve in the supply piping outside the jacket where local code or the utility requires it.
  5. Support the piping with hangers, not by the boiler or its accessories.
  6. Purge all air from the gas supply piping.
  7. Check the boiler and its gas connection for leaks using a bubble test. Never use an open flame.
  8. For pressure tests below 13 in. w.c., close the manual main shutoff valve.
  9. For pressure tests above 13 in. w.c., disconnect the boiler and gas valve from the supply piping.
  10. Use pipe dope that is compatible with propane, applied sparingly to male threads only so it does not block gas flow.

Applies to: CGi-25 to CGi-8 gas-fired boilers, natural gas and propane

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Weil-McLain CGi Series 5 boiler manual, p. 38. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.