Weil-McLain · Boiler troubleshooting
Connect gas supply piping to the boiler
What is going on
Gas piping must be leak-checked before the boiler is placed in operation. Remove the jacket front panel and follow the gas supply piping layout in Figure 25.
Check in this order
- Remove the jacket front panel.
- Install a drip leg at the inlet of the boiler gas connection. Extend it to the floor with pipe between cap and tee if the local utility requires it.
- Install a ground joint union for servicing where required.
- Install a manual shutoff valve in the supply piping outside the jacket where local code or the utility requires it.
- Support the piping with hangers, not by the boiler or its accessories.
- Purge all air from the gas supply piping.
- Check the boiler and its gas connection for leaks using a bubble test. Never use an open flame.
- For pressure tests below 13 in. w.c., close the manual main shutoff valve.
- For pressure tests above 13 in. w.c., disconnect the boiler and gas valve from the supply piping.
- Use pipe dope that is compatible with propane, applied sparingly to male threads only so it does not block gas flow.
Applies to: CGi-25 to CGi-8 gas-fired boilers, natural gas and propane
More boiler guides
Related
Weil-McLain error codes · Weil-McLain parts · Weil-McLain tips · Calculators and reference tables
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: Weil-McLain CGi Series 5 boiler manual, p. 38. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.