Weil-McLain · Boiler troubleshooting

Connect gas supply piping and check for leaks

SlimFit Series 3

What is going on

Gas piping connection and leak test procedure at the boiler.

Check in this order

  1. Remove the jacket front panel.
  2. Install a union for servicing, which is recommended.
  3. Install a manual shutoff valve in the gas supply within 6 feet of the boiler. In Canada the installer must identify the valve.
  4. Support the piping with hangers, not by the boiler or its accessories.
  5. Purge all air from the gas supply piping.
  6. Use two wrenches hold the boiler gas connection still with one while tightening with the other.
  7. Check the boiler and its gas connection for leaks with a soapy water bubble test. Never use an open flame.
  8. Use propane-compatible pipe dope sparingly on male threads only.

Applies to: SlimFit boiler gas connection

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Weil-McLain SlimFit Series 3 boiler manual, p. 48. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.