Weil-McLain · Boiler troubleshooting
Commissioning verification checklist
What is going on
Confirm all commissioning items are complete before leaving the boiler. The list covers controls, water, air purge, condensate, thermostat wiring, combustion, gas input and owner handover.
Check in this order
- Confirm the control is programmed correctly and the system is filled with water and air purged.
- Confirm water chemistry and inhibitor per page 79.
- Confirm automatic air vents, if used, are opened one full turn.
- Confirm the condensate trap is filled and thermostat wiring has no stray voltage.
- Confirm burner flame and combustion are verified per page 82.
- Confirm space heating and DHW control operation, and test any field-installed controls.
- Cycle the boiler with the thermostat and confirm it starts and stops correctly.
- Confirm measured gas input and incoming gas pressure.
- Set the room thermostat and DHW aquastat as required.
- Complete the installation certificate, warranty card and leave the instructions with the owner.
Applies to: SlimFit Series 2 commissioning
More boiler guides
Related
Weil-McLain error codes · Weil-McLain parts · Weil-McLain tips · Calculators and reference tables
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: SlimFit Series 2 boiler manual 550-100-561/1225, p. 84. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.