Chimney draft venting requirements

CGi Series 5

What is going on

Natural draft venting through a vertical vent or chimney, Category I. Vent sizing is a general guide only. Code requirements govern.

Check in this order

  1. Inspect the existing chimney before installing. Clean or replace any perforated pipe or lining.
  2. Use double wall B-vent or a lined chimney approved under NFPA 54 / ANSI Z223.1.
  3. Extend the chimney at least 3 ft above the roof penetration and at least 2 ft above any building part within 10 ft.
  4. Do not connect to a mechanical draft system that can run under positive pressure.
  5. Keep 2 inch clearance from combustibles to the vent pipe.
  6. Do not use a chimney that serves an open fireplace.
  7. Keep horizontal runs short and support longer runs with hangers.
  8. Do not vent into the bottom of the chimney. The vent pipe must not go past the inside wall of the chimney.
  9. Firestop any vent passing through floors or ceilings.
  10. Size the vent connector per the vent connector diameter table.

Applies to: CGi-25 to CGi-8

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: CGi Series 5 Gas-Fired Water Boiler boiler manual, p. 18-19. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.