Weil-McLain · Boiler troubleshooting
Chimney draft venting requirements
What is going on
Natural draft venting through a vertical vent or chimney, Category I. Vent sizing is a general guide only. Code requirements govern.
Check in this order
- Inspect the existing chimney before installing. Clean or replace any perforated pipe or lining.
- Use double wall B-vent or a lined chimney approved under NFPA 54 / ANSI Z223.1.
- Extend the chimney at least 3 ft above the roof penetration and at least 2 ft above any building part within 10 ft.
- Do not connect to a mechanical draft system that can run under positive pressure.
- Keep 2 inch clearance from combustibles to the vent pipe.
- Do not use a chimney that serves an open fireplace.
- Keep horizontal runs short and support longer runs with hangers.
- Do not vent into the bottom of the chimney. The vent pipe must not go past the inside wall of the chimney.
- Firestop any vent passing through floors or ceilings.
- Size the vent connector per the vent connector diameter table.
Applies to: CGi-25 to CGi-8
More boiler guides
Related
Weil-McLain error codes · Weil-McLain parts · Weil-McLain tips · Calculators and reference tables
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: CGi Series 5 Gas-Fired Water Boiler boiler manual, p. 18-19. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.