SVF 500/600 Series 1

What is going on

Final wiring and settings check before the boiler is put back in service.

Check in this order

  1. Inspect all boiler wiring for good condition and secure attachment.
  2. Verify all connectors are fully inserted.
  3. Verify the ground wires are connected to the jacket right side and the control tray cover.
  4. Go through all control settings on the display and adjust as needed.
  5. Check the settings of any external limit controls and set them for the system design.

Applies to: SVF 500/600 boilers

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Weil-McLain SVF 500/600 boiler manual, p. 114. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.