Check the site before setting the boiler. Gas controls must be protected from dripping or spraying water and rain.
Check in this order
- Confirm nearby system water, venting, gas, electrical power and condensate drain connections.
- Remove combustible materials, gasoline and flammable liquids from the area.
- Never install on carpeting, even on a foundation.
- Verify the mounting surface is level and rated for the load.
- Mount the boiler above floor height as required in garages and protect it from vehicle damage.
- If replacing an existing boiler, correct oxygen-causing leaks, undersized expansion tank and lack of freeze protection first.
Applies to: All SlimFit Series 2 models
More boiler guides
Related
Weil-McLain error codes · Weil-McLain parts · Weil-McLain tips · Calculators and reference tables
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: SlimFit Series 2 boiler manual, p. 6. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.