The boiler circulator runs in the boiler loop. Primary/secondary piping is recommended to keep proper flow through the heat exchanger.
Check in this order
- Connect the boiler circulator to the EP7 dry contact terminals 1 and 2.
- Use a relay or starter if the circulator draws more than 10 A.
- Install a fused disconnect or service switch rated 15 A for the circulator load.
Applies to: SlimFit 550/750 Series 3 boiler
More boiler guides
Related
Weil-McLain error codes · Weil-McLain parts · Weil-McLain tips · Calculators and reference tables
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: SlimFit Series 3 boiler manual, p. 52. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.