What is going on

Horizontal units can hang from roof rafters or joists, or sit on a raised platform. Plan for service and drain access in either case.

Check in this order

  1. Pick the location with service and required clearances in mind (see clearance figure 15).
  2. For a platform, build a raised wood frame covered with plywood. If it sits over finished space, add an auxiliary drain pan under the unit.
  3. Leave 8 in. of service clearance below the unit for the condensate trap.
  4. Keep a service platform in front of the unit. In a crawl space, cement blocks can serve as the support.
  5. Run the auxiliary drain line so water leaving it is easy for the homeowner to see.
  6. If needed, use a condensate pump rated for condensing furnaces to meet slope. Protect the discharge line to the outside from freezing.
  7. Hang straps so both ends are supported. Straps must not block the plenum or exhaust piping. Support cooling coil and plenums separately.

Applies to: Horizontal installation, attic or crawl space

More furnace guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Allied 92G1UH installation manual, p. 16 (PDF p. 16). Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.