Used for horizontal units set on a raised platform or suspended in an attic or crawl space.

Check in this order

  1. Select a location that keeps service and required clearances.
  2. Build a raised wooden frame and cover it with plywood. Use an auxiliary drain pan under the unit if installed over finished space.
  3. Leave 8 in of service clearance below the unit for the condensate trap.
  4. Provide a service platform in front of the unit. In a crawl space, cement blocks can serve as support.
  5. Route the auxiliary drain so water is easy to notice.
  6. If needed, use a condensate pump rated for condensing furnaces. Protect the discharge line to the outside from freezing.
  7. Install exhaust, condensate and intake piping per the instructions.

Applies to: Horizontal installs in attic or crawl space

More furnace guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Allied 92G1UH installation instructions manual, p. 16. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.