What is going on

Only do this with the furnace disconnected from line voltage. The door switch moves with the junction box.

Check in this order

  1. Make sure the furnace is not connected to line voltage.
  2. Disconnect the wires from the door switch.
  3. Remove the two screws holding the junction box; leave its wires connected.
  4. Remove the 7/8 in. plug from the opposite hole and drill two 3/16 in. holes at the marked dimples.
  5. Mount the junction box on the opposite side using the same two screws; use only blunt-tip screws.
  6. Move the plug to the old location and install two 1/4 in. plugs from the parts bag in the empty holes.
  7. Squeeze the door switch retaining arms with a flat screwdriver and pry the door switch out.
  8. Install the door switch in the opposite opening and reconnect the wires.

Applies to: Electrical junction box relocation

More furnace guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: 96V series installation instructions, p. 76-77. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.