Duct layout and return air requirements for the furnace.
Check in this order
- Size ducts per ACCA Manual D and install them per NFPA 90.
- If a cooling coil is used, install the furnace upstream of the coil or in parallel with it. Parallel dampers must stop chilled air entering the furnace.
- Use flexible connectors on supply and return to reduce vibration.
- Route returns away from the living area where possible to cut noise.
- If supply ducts carry air outside the furnace room, seal the return to the furnace and terminate it outside that space.
- Make sure the return duct includes provision for return air filters.
- On side return upflow installs, remove the insulation around the opening in the blower compartment.
- Cut the return opening using the locating notches on the side panels and the outline drawing dimensions.
- If a 3/4 in flange is needed, extend the cut as shown, cut corners diagonally and bend outward.
- If no flange is needed and a filter frame is used, cut along the knockout guidelines.
- Connect supply and return ducts to the furnace using the outline drawing sizes and locations.
- When replacing a furnace, clean out old ductwork, cover registers with thin cloths and run the fan for 10 minutes. Remove the cloths before starting the furnace.
Applies to: UH1/DH1 furnaces
More furnace guides
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: Trane installer's guide 18-CD29D1-11, pp. 9-11. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.