Daikin · Water heater · Startup
Test operation of all hot water generation systems
What happens, in order
- Confirm cascade settings and air release are complete.
- Open the stop valve on the heat source unit.
- Close the heat source and cascade front panels and the tank control board cover. Confirm power is on to all units.
- On the remote controller, set mode 20, first code 8, second code 03 (test operation).
- Press On/Off and run all hot water generation systems.
- If the unit stops with no error code, test operation is complete. If an error appears, cut power, correct it using the error code table, then repeat the test.
- Press Cancel to return to the basic screen.
Timings and thresholds
| Item | Value |
|---|---|
| Power on before starting test operation | 6 hours |
| Test operation run time | about 20 minutes |
Codes you may see during this
Applies to: All hot water generation systems on the loop
More Daikin water heater sequences
Related
Take it to the job
Sequences of operation, error codes and tips work offline in the HVACopedia app.
Source: Mega-Q installation manual, p. 43. Written in our own words; timings can differ by model and software version, so check the manual for your exact unit.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.