Daikin · Water heater · Other
Airtight test and vacuum drying procedure
What happens, in order
- Use tools dedicated to R410A and charge hoses with Schrader valve depressors.
- Connect nitrogen, refrigerant tank and vacuum pump to the heat source unit per the system diagram.
- Pressurize from the liquid or gas stop valve service port to 580 psi (4.0 MPa) with nitrogen.
- Hold for 24 hours and check for pressure drop.
- Fix any leak and repeat the airtight test if pressure drops.
- Evacuate from the liquid and gas stop valve service ports to 500 microns or less.
- Hold the system in vacuum for 1 hour and confirm the vacuum gauge does not rise.
- In rainy season, after 2 hours of evacuation, pressurize with nitrogen to 375,000 microns (vacuum break) and evacuate again for 1 hour to 500 microns or less.
- If 500 microns cannot be reached in 2 hours, repeat vacuum break and vacuum drying, then hold 1 hour and confirm the gauge stays flat.
Timings and thresholds
| Item | Value |
|---|---|
| Airtight hold | 24 hours |
| Initial vacuum drying | more than 2 hours |
| Vacuum hold check | 1 hour |
| Rainy-season re-evacuation | 1 hour |
Applies to: Mega-Q refrigerant circuit
More Daikin water heater sequences
Related
Take it to the job
Sequences of operation, error codes and tips work offline in the HVACopedia app.
Source: Daikin Mega-Q installation manual, p. 32. Written in our own words; timings can differ by model and software version, so check the manual for your exact unit.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.