Electrician checks on transmission wiring, power supply wiring, and insulation before the unit is energized.

Check in this order

  1. Check transmission wiring for mis-wiring and loose screws.
  2. Check power supply and ground wiring for mis-wiring and loose screws.
  3. Measure the insulation of the main power supply circuit with a 500V DC insulation resistance tester.
  4. Do not use an insulation resistance tester on low voltage circuits.

Applies to: Mega-Q hot water generation system, electrical installation

More water heater guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Daikin Mega-Q installation manual, p. 66 of 68. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.