Layout drawing for DHW piping. Piping must be field verified by the heating contractor. Key points: install the relief valve on each tank per code, fit shut-off valves, and use a precharged expansion tank wherever a backflow preventer is installed.
Check in this order
- Install the T&P relief valve on each tank in a way that meets local code.
- Fit shut-off valves on the DHW supply and cold water lines.
- Run a discharge pipe from the relief valve and a drain.
- Where a backflow preventer is installed, add a precharged expansion tank per local plumbing code.
- Fit a thermostatic mixing or anti-scald valve on the DHW outlet.
- Field verify the full piping arrangement, since the drawing is conceptual.
Applies to: Vitocell 100-V CVWC
More water heater guides
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: Vitocell 100-V CVWC Technical Data Manual, p. 17. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.