Voltage checks at start-up

D5FCFA Ceiling/Floor Ductless

What is going on

Check voltages at the outdoor disconnect, outdoor terminal block and indoor unit before running the system.

Check in this order

  1. Measure 1(L1) to GND and 2(L2) to GND at the outdoor unit disconnect.
  2. Measure the same points at the outdoor unit terminal block.
  3. Measure 1(L1) to 2(L2) at the outdoor terminal block.
  4. Measure 1(L1) to GND, 2(L2) to GND, 1(L1) to 2(L2), and 2(L2) to 3(S) at the indoor unit.
  5. Record readings on the Voltage Check section of the start-up checklist.

Applies to: Single zone ductless start-up

More mini-split guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Carrier D5FCFA installation manual, p. 23. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.