Carrier · Mini-split troubleshooting
Start-up leak check and evacuation
What is going on
Piping checks to complete during start-up of the ductless system.
Check in this order
- Hold the system at 500 psig (maximum 550 psi) for at least 30 minutes using dry nitrogen. Never use air or oxygen-containing gases.
- Use the Triple Evacuation Method or the Deep Vacuum Method as outlined in the installation manual.
- Confirm the system holds 500 microns for 1 hour after deep vacuum.
- Confirm the line set diameter matches the evaporator connections.
- For conventional fan coils, confirm the line set matches the outdoor unit size.
- Measure the liquid line length, calculate the additional charge, and record the final charge amount.
Applies to: Refrigerant piping
More mini-split guides
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: Carrier D5FSHA installation manual, p. 28. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.