Carrier · Mini-split troubleshooting

Start-up leak check and evacuation

D5FSHA

What is going on

Piping checks to complete during start-up of the ductless system.

Check in this order

  1. Hold the system at 500 psig (maximum 550 psi) for at least 30 minutes using dry nitrogen. Never use air or oxygen-containing gases.
  2. Use the Triple Evacuation Method or the Deep Vacuum Method as outlined in the installation manual.
  3. Confirm the system holds 500 microns for 1 hour after deep vacuum.
  4. Confirm the line set diameter matches the evaporator connections.
  5. For conventional fan coils, confirm the line set matches the outdoor unit size.
  6. Measure the liquid line length, calculate the additional charge, and record the final charge amount.

Applies to: Refrigerant piping

More mini-split guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Carrier D5FSHA installation manual, p. 28. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.